Launch timing, pricing and absorption in Bengaluru are often planned around a metro line or a road that has not opened yet. This page keeps the current official dates in one place, as reported in BREI's briefings. Each row gives the date it was reported, and links to the briefing behind it.

Metro

Line Stretch Current target Reported
ORR metro Silk Board to KR Puram, 19.75 km Mid-2027, subject to statutory clearances 23 Oct 2026
Airport metro Hebbal to the airport Not before September 2027 23 Oct 2026
Airport metro KR Puram to Hebbal December 2027, BMRCL's aim 23 Oct 2026
Pink Line, elevated Kalena Agrahara to Tavarekere, 7.5 km, six stations Opening set for 13 November 2026 6 Nov 2026
Pink Line, underground Dairy Circle to Nagawara via MG Road, 13.76 km 2027 6 Nov 2026

Suburban rail

None of the four lines is running. The project was due to be complete in October 2026.

Line Route Length Current target
Mallige Benniganahalli to Chikkabanavara 25 km December 2028
Kanaka Heelalige to Rajanukunte 46 km 2029
Sampige KSR to Devanahalli and the airport 41 km March 2030
Parijaata Kengeri to Whitefield 35 km March 2030

Reported on 1 October 2026.

Roads

Project Stretch Current position Reported
Ejipura flyover Ejipura to Kendriya Sadan junction End of December 2026 is the internal target for the elevated stretch; the Sarjapur Road ramps are expected in 2027 26 Oct 2026
Ballari Road elevated road UAS Staff Quarters to Mekhri Circle Closed to buses and goods vehicles for 18 months from 6 November 2026, to May 2028 6 Nov 2026
Peripheral Ring Road-2 52 km, Hosur Road to Tumakuru Road via Mysuru Road Final notification issued in September 2026, for about 1,427 acres 12 Oct 2026
Road grid outside GBA limits Bengaluru Urban district, outside the Greater Bengaluru Authority's limits Notified; land inside a notified road must stay vacant 19 Oct 2026

How to use these dates

  • Treat a target as a date, not a service. Several of these projects have moved more than once. The ORR metro was aimed at 2026 and is now due in mid-2027. The suburban rail line to the airport is now due in March 2030, 41 months after its original deadline.
  • Build the base case on what runs today. Absorption and pricing that assume a line will be open at launch carry its schedule risk.
  • Check land against notifications, not only approvals. An approval does not lift an acquisition notification, and land inside a notified road must stay vacant.
  • Plan construction logistics around closures. Goods vehicles cannot use the Ballari Road stretch until May 2028.

How this page is kept

A row changes when a BREI briefing reports a new date. The date beside each row is the date of that report, so a row may be older than the page.

BREI applies these timelines to individual sites in its feasibility studies. The supply lined up around each corridor is on the pipeline page.