  • Bannerghatta Road's metro goes for its safety inspectionInfrastructure

    The elevated metro on Bannerghatta Road had its statutory safety inspection on 6–8 October. The safety commissioner raised observations, which BMRCL is addressing, and the state government has asked the Prime Minister for an inauguration date. No opening date has been announced. What opens first is 7.5 km, Kalena Agrahara to Tavarekere, with an interchange at Jayadeva.

  • Bengaluru's suburban rail was due this month. None of its four lines is runningInfrastructure

    Bengaluru's suburban rail was due to be complete in October 2026. None of its four lines is running. The first is now due in December 2028. The line to Devanahalli and the airport is due in March 2030, 41 months past the original deadline.