TopicsMetro & rail
Bengaluru metro and suburban rail: current dates and what they mean for real estate
Metro and rail dates shape launch timing, pricing and land values across Bengaluru, and most of them have moved at least once. This page collects BREI's briefings on each line and where it stands.
Where things stand
As ofThe operating metro network is about 103.6 km since the Pink Line's elevated stretch opened on 13–14 November 2026. The state's target is more than 170 km within 18 months. More
Trial runs began on the ORR metro, Silk Board to KR Puram, in November 2026; opening is targeted for mid-2027. More
The Sarjapur–Hebbal Red Line is dated April 2033 and still has no central approval; the state asked the Prime Minister for it on 13 November 2026. More
None of the four suburban rail lines is running; the first is due in December 2028. More
Briefings on metro & rail
Newest first. 5 briefings.
- Bengaluru's metro passed 100 km on 13 November; the 170 km target rests on the airport lineInfrastructure
The Prime Minister inaugurated the Pink Line's 7.5 km elevated stretch, Kalena Agrahara to Tavarekere, on 13 November, and passenger service began at 6 am on 14 November. Bengaluru's operating metro network is now about 103.6 km. Two days before the opening, the state's Bengaluru Development Minister set the next target: more than 170 km within 18 months. He called it a challenging target.
- The Sarjapur–Hebbal metro is now dated April 2033, and still has no central approvalInfrastructure
Namma Metro's Phase 3A, the Red Line from Sarjapur Road to Hebbal through the city centre, is dated April 2033 in its revised detailed project report. The earlier date was 2031. The Centre's approval, which was expected in October, has not been given, and civil work cannot start without it.
- The ORR metro, Silk Board to KR Puram, is now due in mid-2027Infrastructure
The metro along the Outer Ring Road, 19.75 km from Silk Board to KR Puram, is now targeted to open in mid-2027, subject to statutory clearances. BMRCL had aimed to open it in 2026. Trial runs began in November: a test train ran from the Baiyappanahalli depot to Benniganahalli on 7 November and on to Doddanekundi on 10 November.
- Bannerghatta Road's elevated metro opened on 13 November, with passenger service from 14 NovemberInfrastructure
The elevated metro on Bannerghatta Road, 7.5 km from Kalena Agrahara to Tavarekere, was inaugurated by the Prime Minister on 13 November, and passenger service began at 6 am on 14 November. It had been due on 15 August. The stretch took Bengaluru's operating metro network from 96.1 km to about 103.6 km.
- Bengaluru's suburban rail was due this month. None of its four lines is runningInfrastructure
Bengaluru's suburban rail was due to be complete in October 2026. None of its four lines is running. The first is now due in December 2028. The line to Devanahalli and the airport is due in March 2030, 41 months past the original deadline.
Guides
- Bengaluru infrastructure timelines: metro, suburban rail and road projects, and their current dates
Current target dates for Bengaluru's metro lines, suburban rail and major road projects, as reported in BREI briefings, and what the dates mean for project launches and land decisions.
Micro-markets in these briefings
South Bengaluru · Sarjapur & ORR Belt · North Bengaluru · Central Bengaluru · East / IT Corridor
Metro and rail, in brief
- Which Bengaluru metro lines open next?
- The Pink Line's underground section to MG Road and Nagawara, and the ORR line from Silk Board to KR Puram, are both due in 2027; the airport line follows, with its last section, KR Puram to Hebbal, due between December 2027 and early 2028. (As reported in November 2026.)
- Should a project's pricing assume a metro line will be open?
- BREI's view is to underwrite on what runs today and treat an opening date as a range. Several Bengaluru lines have moved more than once; the Bannerghatta Road stretch was first dated December 2025 and opened in November 2026.