The Prime Minister inaugurated the Pink Line's 7.5 km elevated stretch, Kalena Agrahara to Tavarekere, on 13 November, and passenger service began at 6 am on 14 November. Bengaluru's operating metro network is now about 103.6 km. Two days before the opening, the state's Bengaluru Development Minister set the next target: more than 170 km within 18 months. He called it a challenging target.

What has to open to get there

Section Length Current target
Pink Line underground, Dairy Circle to Nagawara 13.76 km 2027: March in a July review, May in October reports
ORR line, Silk Board to KR Puram 19.75 km Mid-2027; trial runs began in November 2026
Airport line, Hebbal to the airport about 27.4 km Not before September 2027
Airport line, KR Puram to Hebbal about 11 km December 2027 was BMRCL's aim in October; earlier reports put it in early 2028

The first three sections take the network to roughly 165 km. Passing 170 km needs the KR Puram–Hebbal section as well, which has the latest date of the four.

For developers, landowners and capital partners

Every section in the table has moved at least once. The Pink Line stretch that opened on 13 November was first dated December 2025. A launch, a land price or a joint development that assumes one of these lines should be underwritten on what runs today, with the opening date treated as a range rather than a fixed month.